APPLICATION
Strictly follow installation procedures as defined in method statements, application manuals and working instructions which must always be adjusted to the actual site conditions.
Formwork
Ensure formwork is secure and watertight to prevent movement and leaking during placing and curing.
Working in thick sections
Do not pour more than 100 mm of layer thickness without addition of aggregates.
Small localized repairs
Small volume mixing may carried out with a suitable low-speed (500 rpm) drill and mixing paddle. After mixing, stir lightly with a spatula for a few seconds to release any entrapped air. The micro-concrete is then poured immediately into the prepared formwork.
Large repairs
When carrying out large scale repairs or column / beam jacketing, ensure sufficient pressure head is maintained for uninterrupted concrete flow. Formwork must be firmly placed and kept watertight. When placing micro-concrete over large area, it is important to maintain a continuous flow throughout the process. Work sequence and equipment must be properly organized to ensure an uninterrupted flow of micro-concrete. Ensure proper air displacement when pouring. In large areas, micro-concrete may be mixed and pumped using heavy duty screw feed and piston pumps. Equipment suitability should be tested and checked prior to actual grouting works.
Cold weather working
Consider storing bags in a warm environment and using warm water to assist with achieving strength gain and maintaining physical properties.
Hot weather working
Consider storing bags in a cool environment and using cold water to assist with controlling the exothermic reaction to reduce cracking and maintaining physical properties.